Ready for Takeoff: Marketplace Nears Launch

Written by GracoRoberts | Jul 6, 2026 1:09:10 PM

The Marketplace has been a key project for our family of brands for some time now. And we are so excited to share that we are now entering the home stretch toward development completion.

Marketplace is a unified ecommerce shopping platform that will bring GracoRoberts, Silmid, and SkyGeek together in one place.

Customers will be able to:

  • Shop products from all three businesses through one website.
  • Find products more easily.
  • Place orders through a single system.
Employees will benefit from:
  • One shared selling platform.
  • Modern tools for processing and fulfilling orders.
  • Better collaboration between the businesses.

Rollout Plan: Phase 1 - GracoRoberts

Instead of launching all three businesses at the same time, the Marketplace will be released in stages.

GracoRoberts will be the first business to use the new platform.

At launch:

  • Customers will only see GracoRoberts products and inventory (stock available for sale).
  • Orders will be fulfilled only through GracoRoberts.

Later phases will add:

  • SkyGeek products and inventory.
  • Silmid products and inventory.
  • Cross-business integration (the ability to buy products from multiple businesses in one place).
  • Dropship capability (products shipped directly from suppliers to customers).

This phased approach helps the team identify and fix issues before expanding to the other businesses.

Launch Date

The current target launch date is August 24

The team is working hard to meet this date, but some work is still in progress. If the timeline changes, everyone will be notified by email.

The focus is on launching a high-quality system, not simply meeting the deadline.

Progress Update

1. Major System Components Being Handed to RED

The internal development team is finishing several important systems and preparing to hand them over to RED TECHNOLOGY (the external software development partner).

Key items include:

  • Reservation API – a system that allows different software applications to share reservation information.
  • Order API – a system that allows different software applications to share order information.

API (Application Programming Interface) = a tool that allows different software systems to communicate with each other.

Once RED receives these systems, they can begin their part of the work.

The teams will then hold regular Developer Triage meetings to review issues and coordinate fixes.

Triage = reviewing, prioritizing, and resolving problems.

2. Storefront and Inventory Availability

The Storefront is the website customers will use.

The team is finalizing the connection between the storefront and live inventory data.

This is important because it enables:

  • Accurate stock information.
  • Add to Cart functionality.
  • Checkout and purchasing.

A few software bugs still need to be fixed before this work is complete.

3. Enterprise Portal and Product Specifications

The Enterprise Portal is the central system for managing product information and specifications across the businesses.

The portal is currently:

  • Being tested.
  • Having issues corrected (remediation)

After that work is complete:

The Quality team will begin specification mapping (spec mapping).

Spec (Specification) = detailed information about a product, such as:

  • Size
  • Material
  • Performance requirements
  • Technical attributes
  • Search products accurately.
  • Filter products correctly.
  • View complete product details.

Spec mapping = organizing and linking this information so customers can:

Business Analysts (BAs) help connect business needs with technical solutions.

They are:

  • Cleaning specification data.
  • Creating a repeatable process for future data cleanup.

4. GracoRoberts Operations Testing

Next week, the GracoRoberts Operations team will begin testing important document processes in Crescendo (the business workflow system being used for these documents).

Documents being tested include:

CoA (Certificate of Analysis) Integration

A document that confirms a product has been tested and meets required standards.

Test Report Integration

A document showing the results of testing performed on a product.

The team will also test:

  • Pick Ticket = instructions used by warehouse staff to collect products for an order.
  • Packing Slip = document included with a shipment showing what is inside.

The goal is for Operations to formally approve these processes before launch.

5. Other Supporting Work

ASN (Advance Ship Notice) Completed

A document sent before products arrive, letting the customer know:

  • What is being shipped.
  • When it is expected to arrive.

The ASN build is complete.

Commercial Invoice

A Commercial Invoice can now be generated.

This is an official document used in international shipping that includes:

  • Product details.
  • Values.
  • Customs information.

Some functionality still depends on work being completed by each business unit.

SAP Work

SAP is enterprise software system currently used by SkyGeek and GracoRoberts (classified)for business operations such as inventory, purchasing, and finance.

SAP-related tasks have been handed to Vision33 (our specialist vendor), and the team is waiting for updates.

We are also creating documentation that tracks every part of the build and shows how different systems connect, helping make sure nothing is missed as each business joins the Marketplace.

What Each Team Is Doing Next

The teams have clear next steps. GR Operations is testing the paperwork (document) workflows, Quality is getting ready to organize product details once the main portal is cleaned up, and our developers are handing off the big technical pieces to our partner team, RED, to keep things moving.

Quick Summary

If you read only one section, read this one.

  • We're building one online store for all three businesses. GracoRoberts, Silmid, and SkyGeek will share a single Marketplace where customers can shop across all of them.
  • GracoRoberts will launch first. At first you'll only see GracoRoberts products and stock; SkyGeek and Silmid join in later phases.
  • The target launch date is August 24. The team is working hard to finish, but there could be delays, and if the date moves, everyone will get an email.
  • Important development work is close to completion, but some bug fixes remain.
  • Operations, Quality, Business Analysts, and Developers all have clear tasks to complete before launch.